Oranienburg on the Havel
Installation of a 432 m long DN 500 pipe section using the controlled horizontal directional drilling technique at Oranienburg on the Havel
Crossing the pipeline underneath a canal, while at the same time protecting the adjoining nature preservation areas, was the challenge for the planners and contractors when installing a new DN 500 supply pipe.
The canal and bank areas necessitated a culvert with a total length of 435 m. It was therefore decided to complete this section with the aid of the controlled horizontal directional drilling technique.
It was the first time that such a distance was to be covered with DN 500 pipes using this technique.
72 pipes with the restrained positive-locking TYTON®-BLS® socket connection were assembled to make up the overall length.
The pipe was then drawn in within three hours with a required tractive force of a maximum of 443 kN. The pressure test discovered no problems at all, and the construction time was less than one week.
Pipe material/pipe connection Pipes of ductile cast iron to DIN EN 545 Restrained positive-locking TYTON®-BLS® socket connection
Pipe outer protection Cement mortar coating (ZMU) to DIN 30 674, Part 2 | | |
|
 Schematic view of the control horizontal directional drilling technique
 Impact of the widening head on the drill
 Inclined pit
|
« Back